Weekly Project Update

FORREST TRAILS PLAYSCAPE IMPROVEMENTS

Placeholder

Pat Tims

THIS WEEK'S ACCOMPLISHMENT

    MATERIALS RECEIVED TO SITE
    BUSHINGS PLACED
    SURFACE COMPLETED
Excavation 1.jpg

BUSHINGS PLACED

NEXT WEEK'S ACTIVITIES

    DECISION ON LANDSCAPING
    DEMOBILIZE
Excavation 1.jpg

SURFACE INSTALLATION

Excavation 1.jpg

SURFACE COMPLETED

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.