THIS WEEK'S ACCOMPLISHMENT

    Ash Masonry - Removed Column Capital West Elevation
    Ash Masonry - Set Cor-1,2,3 Stones South Elevation
    Ash -Masonry - Set Cor-1,2,3 Stones West Elevation, Mortared Cor-1,2,3 Stones West Elevation
    Stanton Studios - Installed Protective Glass E-301,302,303,304,305
    Stanton Studios - Installed Protective Frame S-306
    ATC - Finished Cleaning Level 4 West Elevation
Excavation 1.jpg

S-306 Protective Glass Installed

NEXT WEEK'S ACTIVITIES

    Ash Masonry - Mortar Cor-1,2,3 South Elevation
    Ash Masonry - Carpentry Work West Elevation Gables, South Elevation Gables
    Ash Masonry - Prepping North Elevation Capitals For Repairs
    Stanton Studios - Restoration Process S-302,303,304,305,306 (50% Complete)
    Braun & Butler - Deliver Column Capital To Advanced Architectural Stone
Excavation 1.jpg
    ATC - Cleans East Elevation

First Section Of Column Capital Removed

Excavation 1.jpg

West Elevation Capital Removed