Weekly Project Update
FUMC

Pat Tims
Aug 22, 2025
THIS WEEK'S ACCOMPLISHMENT
- Ash Masonry - Removed Column Capital West Elevation
- Ash Masonry - Set Cor-1,2,3 Stones South Elevation
- Ash -Masonry - Set Cor-1,2,3 Stones West Elevation, Mortared Cor-1,2,3 Stones West Elevation
- Stanton Studios - Installed Protective Glass E-301,302,303,304,305
- Stanton Studios - Installed Protective Frame S-306
- ATC - Finished Cleaning Level 4 West Elevation

S-306 Protective Glass Installed
NEXT WEEK'S ACTIVITIES
- Ash Masonry - Mortar Cor-1,2,3 South Elevation
- Ash Masonry - Carpentry Work West Elevation Gables, South Elevation Gables
- Ash Masonry - Prepping North Elevation Capitals For Repairs
- Stanton Studios - Restoration Process S-302,303,304,305,306 (50% Complete)
- Braun & Butler - Deliver Column Capital To Advanced Architectural Stone

- ATC - Cleans East Elevation
First Section Of Column Capital Removed

West Elevation Capital Removed
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.