top of page


Weekly Project Update
FUMC

Pat Tims
Nov 21, 2025
THIS WEEK'S ACCOMPLISHMENT
- Ash Masonry - Finials 1-B, 1-C Installation Completed South Elevation
- Ash Masonry - Soffit Stones Structural Rods Exposed For Inspection
- Ash Masonry - Hilti Pull Test Scheduled For December 2nd
- Stanton Studios - Repaired Broken Stained Glass Panel Above Sanctuary
- Stanton Studios - N-303 95%, N-304 90%, N-305 85%, N-306 45%, N-307 45% Complete
- Red River Restoration - Installed Hardware - Choir Room

Ash Masonry Setting Finial South Elevation
NEXT WEEK'S ACTIVITIES
- Ash Masonry - Finishes Pointing West Elevation 11/24
- Stanton Studios - Completes Three Sanctuary Windows North Elevation
- Stanton Studios - Installs Protective Glass S-303, S-304, S-305
- Arc Abatement - Removes Bird Excrement
- Burnish Finishes - Repairs W-302, W-303, S-301, N-308

- Red River Finishes Restoration - Hardware W-302, W-303
Finials In Place South View

Finials 1-B, 1-C Set South Elevation
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.