top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

FUMC

Placeholder

Pat Tims

Nov 21, 2025

THIS WEEK'S ACCOMPLISHMENT

    Ash Masonry - Finials 1-B, 1-C Installation Completed South Elevation
    Ash Masonry - Soffit Stones Structural Rods Exposed For Inspection
    Ash Masonry - Hilti Pull Test Scheduled For December 2nd
    Stanton Studios - Repaired Broken Stained Glass Panel Above Sanctuary
    Stanton Studios - N-303 95%, N-304 90%, N-305 85%, N-306 45%, N-307 45% Complete
    Red River Restoration - Installed Hardware - Choir Room
Excavation 1.jpg

Ash Masonry Setting Finial South Elevation

NEXT WEEK'S ACTIVITIES

    Ash Masonry - Finishes Pointing West Elevation 11/24
    Stanton Studios - Completes Three Sanctuary Windows North Elevation
    Stanton Studios - Installs Protective Glass S-303, S-304, S-305
    Arc Abatement - Removes Bird Excrement
    Burnish Finishes - Repairs W-302, W-303, S-301, N-308
Excavation 1.jpg
    Red River Finishes Restoration - Hardware W-302, W-303

Finials In Place South View

Excavation 1.jpg

Finials 1-B, 1-C Set South Elevation

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page