THIS WEEK'S ACCOMPLISHMENT

    ATC - East Elevation Paint Removal & Cleaning Completed
    Ash Masonry - Installed Blocking/Nailers West & South Elevations
    Stanton Studios - 95% Complete on 2-3 South Elevation Sanctuary Windows; Installation Next Week
    Balcony Hardware Installed
    Empire Roofing Reattached Temporary Roofing To Provide Greater Access For Carpentry Repairs
    Advanced Architectural Stone - Continues Working On Shop Drawings
Excavation 1.jpg

East Elevation - Cleaning Completed

NEXT WEEK'S ACTIVITIES

    Ash Masonry - Finish Blocking/Nailers East Elevaiton
    Ash Masonry - Remove Freize Stones Southwest Elevation To Allow Structural Connection Repair
    Stanton Studios - Installs 2-3 Sanctuary Windows South Elevation
    Stanton Studios - Removes 2-3 Sanctuary Windows North Elevation
    Stanton Studios - Continues On Remaining Sanctuary Windows South Elevation
Excavation 1.jpg
    ATC - Removing Paint & Cleaning North Elevation

Men AT Work - West Elevation South Gable