THIS WEEK'S ACCOMPLISHMENT
- ATC - East Elevation Paint Removal & Cleaning Completed
- Ash Masonry - Installed Blocking/Nailers West & South Elevations
- Stanton Studios - 95% Complete on 2-3 South Elevation Sanctuary Windows; Installation Next Week
- Balcony Hardware Installed
- Empire Roofing Reattached Temporary Roofing To Provide Greater Access For Carpentry Repairs
- Advanced Architectural Stone - Continues Working On Shop Drawings

East Elevation - Cleaning Completed
NEXT WEEK'S ACTIVITIES
- Ash Masonry - Finish Blocking/Nailers East Elevaiton
- Ash Masonry - Remove Freize Stones Southwest Elevation To Allow Structural Connection Repair
- Stanton Studios - Installs 2-3 Sanctuary Windows South Elevation
- Stanton Studios - Removes 2-3 Sanctuary Windows North Elevation
- Stanton Studios - Continues On Remaining Sanctuary Windows South Elevation

- ATC - Removing Paint & Cleaning North Elevation
Men AT Work - West Elevation South Gable