THIS WEEK'S ACCOMPLISHMENT

    ATC - Sealed Soffit Stones West, South East Elevations
    Terracon Engineering - Testing Scheduled
    Ash Masonry - Cleaned, Shaped, Prepped Columns For CFRP
    Stanton Studios - Installed Protective Glass Sanctuary Windows North Elevation
    Stanton Studios - Removed N-308 For Repairs
    Red River Restoration - Repaired Sash Lock Mortise W-303
Excavation 1.jpg

Ash Masonry Prepping Columns For CFRP Installation

NEXT WEEK'S ACTIVITIES

    Ash Masonry - Install CFRP Columns West Elevation
    Ash Masonry - Set Clam Shell Finial
    Terracon Engineering - Complete Testing
    ATC - Seals Cor-4's West, South, East Elevations
    Stanton Studios - Repair N-308
Excavation 1.jpg
    Advanced Architectural Stone - Remaining E&D Stones In Production

Stanton Studios - Protective Glass Installation Complete North Elevation

Excavation 1.jpg

ATC - Applying Sealer Soffit Stones West Elevation

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.