top of page


Weekly Project Update
FUMC

Pat Tims
Jan 19, 2026
THIS WEEK'S ACCOMPLISHMENT
- ATC - Sealed Soffit Stones West, South East Elevations
- Terracon Engineering - Testing Scheduled
- Ash Masonry - Cleaned, Shaped, Prepped Columns For CFRP
- Stanton Studios - Installed Protective Glass Sanctuary Windows North Elevation
- Stanton Studios - Removed N-308 For Repairs
- Red River Restoration - Repaired Sash Lock Mortise W-303

Ash Masonry Prepping Columns For CFRP Installation
NEXT WEEK'S ACTIVITIES
- Ash Masonry - Install CFRP Columns West Elevation
- Ash Masonry - Set Clam Shell Finial
- Terracon Engineering - Complete Testing
- ATC - Seals Cor-4's West, South, East Elevations
- Stanton Studios - Repair N-308

- Advanced Architectural Stone - Remaining E&D Stones In Production
Stanton Studios - Protective Glass Installation Complete North Elevation

ATC - Applying Sealer Soffit Stones West Elevation
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.