Weekly Project Update

FUMC

Placeholder

Pat Tims

Oct 17, 2025

THIS WEEK'S ACCOMPLISHMENT

    Stanton Studios - S-304,305 Installed, N- 304,305 Removed
    Red River Restoration - Completed Jamb Stripping, Repairing, Priming, Painting N-304,305
    Red River Restoration - Installed Sash Locks Balcony, Sanctuary Levels, Installed Hardware S-207, N-204
    Ash Masonry - Removed All Cor-4 Stones West Gable, 14 Cor-4 Stones East Gable North Elevation
    CMP - Beam Connections Completed Southwest, Northwest Soffits
    Advanced Architectural Stone - East Elevation Replacement Cor-4 Stones Completed
Excavation 1.jpg

Red River Restoration - N-304,305

NEXT WEEK'S ACTIVITIES

    Stanton Studios - Install Remaining Two Sanctuary Windows South Elevation, Removes Final Two Windows North Elevation
    Ash Masonry - Remove Soffit Stones West Elevation
    Ash Masonry - Remove Remaining Cor-4 Stones East Gable North Elevaiton
    Ash Masonry - Texas Curb Cut Removes Capital Number Eight West Elevation
    ARC Abatement - Abates Remaining Two Sanctuary Windows North Elevation
Excavation 1.jpg
    ATC - Wash, Seal Columns South, East Elevations, Seal Finials Onsite

Red River Restoration - Hardware Installation Family Room

Excavation 1.jpg

CMP - Beam Connection Completed Southwest Soffit

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.