Weekly Project Update
FUMC

Pat Tims
Oct 17, 2025
THIS WEEK'S ACCOMPLISHMENT
- Stanton Studios - S-304,305 Installed, N- 304,305 Removed
- Red River Restoration - Completed Jamb Stripping, Repairing, Priming, Painting N-304,305
- Red River Restoration - Installed Sash Locks Balcony, Sanctuary Levels, Installed Hardware S-207, N-204
- Ash Masonry - Removed All Cor-4 Stones West Gable, 14 Cor-4 Stones East Gable North Elevation
- CMP - Beam Connections Completed Southwest, Northwest Soffits
- Advanced Architectural Stone - East Elevation Replacement Cor-4 Stones Completed

Red River Restoration - N-304,305
NEXT WEEK'S ACTIVITIES
- Stanton Studios - Install Remaining Two Sanctuary Windows South Elevation, Removes Final Two Windows North Elevation
- Ash Masonry - Remove Soffit Stones West Elevation
- Ash Masonry - Remove Remaining Cor-4 Stones East Gable North Elevaiton
- Ash Masonry - Texas Curb Cut Removes Capital Number Eight West Elevation
- ARC Abatement - Abates Remaining Two Sanctuary Windows North Elevation

- ATC - Wash, Seal Columns South, East Elevations, Seal Finials Onsite
Red River Restoration - Hardware Installation Family Room

CMP - Beam Connection Completed Southwest Soffit
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.