Weekly Project Update
FUMC

Pat Tims
Oct 31, 2025
THIS WEEK'S ACCOMPLISHMENT
- Advanced Architectural Stone - E&D-6 Shop Drawings Under Review
- Ash Masonry - Set 2 Cor-4 Replacement Stones
- Ash Masonry - Removed Cor-8, 12 Gutter Stones North Elevation
- Ash Masonry - Explored Columns West Elevation
- Ash Masonry - Field Modified Cor-2,3 For Finial Fit
- Red River Restoration - Stripped, Repaired, Primed N-305,306

Red River Restoration Jamb Work N-305
NEXT WEEK'S ACTIVITIES
- Advanced Architectural Stone - E&D-6 South Fabrication 17 Stones
- Ash Masonry - Remove Remaining Gutter Stones For E&D Inspections
- Red River Restoration - Installs Hardware Balcony, Sanctuary, Mortises N-406
- Stanton Studios - Installs Protective Glass S-301,302,303
- Stanton Studios - Installs Protective Framing N-303,304,305

- Stanton Studios - Restoration Continues N-302,303,304,305,306
Ash Masonry - Removing Cor-8 Gutter Stone North Elevation

Ash Masonry - Carpentry Work Closing East Elevation
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.