Weekly Project Update

FUMC

Placeholder

Pat Tims

Oct 31, 2025

THIS WEEK'S ACCOMPLISHMENT

    Advanced Architectural Stone - E&D-6 Shop Drawings Under Review
    Ash Masonry - Set 2 Cor-4 Replacement Stones
    Ash Masonry - Removed Cor-8, 12 Gutter Stones North Elevation
    Ash Masonry - Explored Columns West Elevation
    Ash Masonry - Field Modified Cor-2,3 For Finial Fit
    Red River Restoration - Stripped, Repaired, Primed N-305,306
Excavation 1.jpg

Red River Restoration Jamb Work N-305

NEXT WEEK'S ACTIVITIES

    Advanced Architectural Stone - E&D-6 South Fabrication 17 Stones
    Ash Masonry - Remove Remaining Gutter Stones For E&D Inspections
    Red River Restoration - Installs Hardware Balcony, Sanctuary, Mortises N-406
    Stanton Studios - Installs Protective Glass S-301,302,303
    Stanton Studios - Installs Protective Framing N-303,304,305
Excavation 1.jpg
    Stanton Studios - Restoration Continues N-302,303,304,305,306

Ash Masonry - Removing Cor-8 Gutter Stone North Elevation

Excavation 1.jpg

Ash Masonry - Carpentry Work Closing East Elevation

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.