top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

FUMC

Placeholder

Pat Tims

Dec 5, 2025

THIS WEEK'S ACCOMPLISHMENT

    Arc Abatement - Bird Excrement Removal Underway
    Ash Masonry - Removed Two Cor-4's & Installed Two Cor-4 Stones North Elevation, Mortared Stones North Elevation
    Ash Masonry - Installed Blocking For Roof Diaphragm Closure
    Ash Masonry - Added Mortar Wash South Elevation
    B&L Construction - Replaced Ceiling Tile Northwest Stairwell, Lowered Debris Netting West & South Elevations
    Red River Restoration - Attached Sash Arms Balcony Windows
Excavation 1.jpg

B&L Construction - Ceiling Tiles Replaced Northwest Stairwell

NEXT WEEK'S ACTIVITIES

    Arc Abatement - Finishes Bird Excrement Removal
    Stanton Studios - Installs Two Sanctuary Windows North Elevation
    Ash Masonry - Sets Finials West Elevation
    Ash Masonry - Finishes Mortar Washes
    Ash Masonry - Repairs Columns West Elevation
Excavation 1.jpg
    ATX Cleaning - Cleans Interior Balcony & Sanctuary Windows, Cleans Doors, Stairwells

Ash Masonry - Orlando Torrez Mortaring Cor-4 Stones North Elevation East Gable

Excavation 1.jpg

Arc Abatement - Removing Bird Excrement West Elevation

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page