Weekly Project Update
FUMC

Pat Tims
Dec 5, 2025
THIS WEEK'S ACCOMPLISHMENT
- Arc Abatement - Bird Excrement Removal Underway
- Ash Masonry - Removed Two Cor-4's & Installed Two Cor-4 Stones North Elevation, Mortared Stones North Elevation
- Ash Masonry - Installed Blocking For Roof Diaphragm Closure
- Ash Masonry - Added Mortar Wash South Elevation
- B&L Construction - Replaced Ceiling Tile Northwest Stairwell, Lowered Debris Netting West & South Elevations
- Red River Restoration - Attached Sash Arms Balcony Windows

B&L Construction - Ceiling Tiles Replaced Northwest Stairwell
NEXT WEEK'S ACTIVITIES
- Arc Abatement - Finishes Bird Excrement Removal
- Stanton Studios - Installs Two Sanctuary Windows North Elevation
- Ash Masonry - Sets Finials West Elevation
- Ash Masonry - Finishes Mortar Washes
- Ash Masonry - Repairs Columns West Elevation

- ATX Cleaning - Cleans Interior Balcony & Sanctuary Windows, Cleans Doors, Stairwells
Ash Masonry - Orlando Torrez Mortaring Cor-4 Stones North Elevation East Gable

Arc Abatement - Removing Bird Excrement West Elevation
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.