Weekly Project Update

FUMC

Placeholder

Pat Tims

Jul 4, 2025

THIS WEEK'S ACCOMPLISHMENT

    Stanton Studios - Installed Protective Glass S-401,E-401,407,N-407
    Stanton Studios - Restoration E-301,302,303,304,305 85% Complete, W-302,303 75% Complete
    Ash Masonry - Removed 3 & Set 4 Cor-4 Stones South Elevation East Rake
    Ash Masonry - Mortared Cor-4 Stones South Elevation East Rake
    Ash Masonry - Southwest Corner Stone Removal
    AAS - Received Shipment 24 Cor-4 Stones
Excavation 1.jpg

Setting Cor-4 Stone South Elevation

NEXT WEEK'S ACTIVITIES

    Stanton Studios - Installs S-301,307,308,401,407
    Stanton Studios Restoration E-301,302,303,304,305 85% Complete, W-302,303 75% Complete
    Red River Restoration - Strip Lintels, Remove Rust, Prime W-301,302,303,E-101,101,201,102,102,103,Grill,202,103, (Windows & Entrance Doors)
    ATC - Tint Sealer & Apply To Cor-4 Stone
    Ash Masonry - Remove E&D-5,6
Excavation 1.jpg
    ATC - Strip Capitals South & East Elevations

South Elevation East Rake

Excavation 1.jpg

Protective Glass S-401

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.