top of page


Weekly Project Update
FUMC

Pat Tims
Jul 4, 2025
THIS WEEK'S ACCOMPLISHMENT
- Stanton Studios - Installed Protective Glass S-401,E-401,407,N-407
- Stanton Studios - Restoration E-301,302,303,304,305 85% Complete, W-302,303 75% Complete
- Ash Masonry - Removed 3 & Set 4 Cor-4 Stones South Elevation East Rake
- Ash Masonry - Mortared Cor-4 Stones South Elevation East Rake
- Ash Masonry - Southwest Corner Stone Removal
- AAS - Received Shipment 24 Cor-4 Stones

Setting Cor-4 Stone South Elevation
NEXT WEEK'S ACTIVITIES
- Stanton Studios - Installs S-301,307,308,401,407
- Stanton Studios Restoration E-301,302,303,304,305 85% Complete, W-302,303 75% Complete
- Red River Restoration - Strip Lintels, Remove Rust, Prime W-301,302,303,E-101,101,201,102,102,103,Grill,202,103, (Windows & Entrance Doors)
- ATC - Tint Sealer & Apply To Cor-4 Stone
- Ash Masonry - Remove E&D-5,6

- ATC - Strip Capitals South & East Elevations
South Elevation East Rake

Protective Glass S-401
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page