Weekly Project Update

FUMC

Placeholder

Pat Tims

Oct 24, 2025

THIS WEEK'S ACCOMPLISHMENT

    ATC - Sealed West Elevation Cor-1,2,3,4 Stones West, East Elevations, Sealed Finials
    Ash Masonry - Removed Capital 4 OH, Freize, Soffit Stones Column 8 West Elevation, Removed Freize Stones West Elevation Above Capitals 1-7
    Ash Masonry - Removed Cor-13,14 Gutter Stones, E&D-4 Stones North Elevation, Removed E&D-1 Stone West Gable North Elevation
    Stanton Studios - Installed Remaining Two Sanctuary Windows South Elevation
    Stanton Studios - Removed Remaining Two North Sanctuary Windows North Elevation
    Advanced Architectural Stone - Delivered Remake Cor-4 Stones East Elevation
Excavation 1.jpg

Texas Curb Cut Removing Capital 4 OH 10-22-2025

NEXT WEEK'S ACTIVITIES

    Red River Restoration - Finish Installing Hardware Balcony Windows, Sanctuary Windows
    Red River Restoration - Strips, Repairs, Primes, Paints Two Remaining Jambs Sanctuary Windows North Elevation
    Ash Masonry - Sets Two Remaining Cor-4 Stones East Elevation, Sets Finials East Elevation
    Arc Abatement - Abates Final Two Sanctuary Windows North Elevation
    Advanced Architectural Stone - Gutter Stones In Production
Excavation 1.jpg
    Advanced Architectural Stone- Received E&D-1 West Gable, Cor-13 Gutter Stone, E&D-4 For Reproduction

Ash Masonry's Forrest Pope Directing Texas Curb Cut Removing Capital 4 OH

Excavation 1.jpg

ATC Applying Tinted Sealer Cor-4 Stones East Elevation

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.