THIS WEEK'S ACCOMPLISHMENT
- ATC - Sealed West Elevation Cor-1,2,3,4 Stones West, East Elevations, Sealed Finials
- Ash Masonry - Removed Capital 4 OH, Freize, Soffit Stones Column 8 West Elevation, Removed Freize Stones West Elevation Above Capitals 1-7
- Ash Masonry - Removed Cor-13,14 Gutter Stones, E&D-4 Stones North Elevation, Removed E&D-1 Stone West Gable North Elevation
- Stanton Studios - Installed Remaining Two Sanctuary Windows South Elevation
- Stanton Studios - Removed Remaining Two North Sanctuary Windows North Elevation
- Advanced Architectural Stone - Delivered Remake Cor-4 Stones East Elevation

Texas Curb Cut Removing Capital 4 OH 10-22-2025
NEXT WEEK'S ACTIVITIES
- Red River Restoration - Finish Installing Hardware Balcony Windows, Sanctuary Windows
- Red River Restoration - Strips, Repairs, Primes, Paints Two Remaining Jambs Sanctuary Windows North Elevation
- Ash Masonry - Sets Two Remaining Cor-4 Stones East Elevation, Sets Finials East Elevation
- Arc Abatement - Abates Final Two Sanctuary Windows North Elevation
- Advanced Architectural Stone - Gutter Stones In Production

- Advanced Architectural Stone- Received E&D-1 West Gable, Cor-13 Gutter Stone, E&D-4 For Reproduction
Ash Masonry's Forrest Pope Directing Texas Curb Cut Removing Capital 4 OH

ATC Applying Tinted Sealer Cor-4 Stones East Elevation