top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

FUMC

Placeholder

Pat Tims

Jul 25, 2025

THIS WEEK'S ACCOMPLISHMENT

    Advanced Architectural Stone - Cor-1,2,3 Stones Onsite.
    Ash Masonry - Removed Remaining Transition Stone Cor-11-,Cor-19
    ATC - Applied Second Coat Of Stripper, Washed South Elevation
    Arc Abatement - S-302,303,304,305,306 Abated
    Stanton Studios W-302,303 Installation Week Of 8/4
    Braun & Butler Delivered Cor-16OH, E&D-5OH To Advanced Architectural Stone
Excavation 1.jpg

ATC - Stripping Continues South Elevation

NEXT WEEK'S ACTIVITIES

    Red River Restoration - Finish Coat E-301,302,303,304,305
    Red River Restoration - Strip, Remove Rust, Prime, Paint Lintels S-302,303,304,305,306
    Ash Masonry - Set Cor-1,2,3 East Elevation
    Ash Masonry - Remove Gutter Stones Southwest Elevation
    Stanton Studios - Finish W-302,303 Installation Week 8/4
Excavation 1.jpg
    ATC - Stripping, Cleaning West Elevation

Cor-1 Stone Ready For Placement

Excavation 1.jpg

Finial Molds Nearing Completion

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page