Weekly Project Update
FUMC

Pat Tims
Jul 25, 2025
THIS WEEK'S ACCOMPLISHMENT
- Advanced Architectural Stone - Cor-1,2,3 Stones Onsite.
- Ash Masonry - Removed Remaining Transition Stone Cor-11-,Cor-19
- ATC - Applied Second Coat Of Stripper, Washed South Elevation
- Arc Abatement - S-302,303,304,305,306 Abated
- Stanton Studios W-302,303 Installation Week Of 8/4
- Braun & Butler Delivered Cor-16OH, E&D-5OH To Advanced Architectural Stone

ATC - Stripping Continues South Elevation
NEXT WEEK'S ACTIVITIES
- Red River Restoration - Finish Coat E-301,302,303,304,305
- Red River Restoration - Strip, Remove Rust, Prime, Paint Lintels S-302,303,304,305,306
- Ash Masonry - Set Cor-1,2,3 East Elevation
- Ash Masonry - Remove Gutter Stones Southwest Elevation
- Stanton Studios - Finish W-302,303 Installation Week 8/4

- ATC - Stripping, Cleaning West Elevation
Cor-1 Stone Ready For Placement

Finial Molds Nearing Completion
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.