top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

FUMC

Placeholder

Pat Tims

Feb 27, 2026

THIS WEEK'S ACCOMPLISHMENT

    Ash Masonry - Repaired Rafters, Attached Roof To Stone, Replaced Roof Decking Southwest Elevation
    Ash Masonry - Removed Cor-8, E&D-6 Stones Southeast Elevation
    Ash Masonry - Replaced Cor-8, E&D-6 Stones Southeast Elevation
    Ash Masonry - Repaired Rafters, Attached Roof To Stone, Replaced Roof Decking Southeast Elevation
    ATC - Finished Sealing The East Elevation, Sealing The North Elevation, Recleaned Arches, Sills For Encapsulant
    ARC Abatement - Encapsulated Stones West Elevation
Excavation 1.jpg

Ash Masonry -Rafter Repairs Southwest Elevation

NEXT WEEK'S ACTIVITIES

    Ash Masonry - Remove Cor-12, E&D-6 Stones Northwest Elevation
    Ash Masonry - Set Cor-12, E&D-6 Stones Northwest Elevation
    Ash Masonry - Repair Rafters, Attach Roof To Stones, Replace Roof Decking
    Ash Masonry - Complete CFRP Capital Columns West Elevation
    Ash Masonry - Replace Gutter Boxes Southwest, Southeast Elevation
Excavation 1.jpg
    ATC- Complete Second Coat Sealer North Elevation, Seal Arches, Sills West Elevation

Roof To Stone Attachments Installed

Excavation 1.jpg

Roof Decking Replaced Southwest Elevation

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page