Weekly Project Update
FUMC

Pat Tims
Feb 27, 2026
THIS WEEK'S ACCOMPLISHMENT
- Ash Masonry - Repaired Rafters, Attached Roof To Stone, Replaced Roof Decking Southwest Elevation
- Ash Masonry - Removed Cor-8, E&D-6 Stones Southeast Elevation
- Ash Masonry - Replaced Cor-8, E&D-6 Stones Southeast Elevation
- Ash Masonry - Repaired Rafters, Attached Roof To Stone, Replaced Roof Decking Southeast Elevation
- ATC - Finished Sealing The East Elevation, Sealing The North Elevation, Recleaned Arches, Sills For Encapsulant
- ARC Abatement - Encapsulated Stones West Elevation

Ash Masonry -Rafter Repairs Southwest Elevation
NEXT WEEK'S ACTIVITIES
- Ash Masonry - Remove Cor-12, E&D-6 Stones Northwest Elevation
- Ash Masonry - Set Cor-12, E&D-6 Stones Northwest Elevation
- Ash Masonry - Repair Rafters, Attach Roof To Stones, Replace Roof Decking
- Ash Masonry - Complete CFRP Capital Columns West Elevation
- Ash Masonry - Replace Gutter Boxes Southwest, Southeast Elevation

- ATC- Complete Second Coat Sealer North Elevation, Seal Arches, Sills West Elevation
Roof To Stone Attachments Installed

Roof Decking Replaced Southwest Elevation
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.