top of page


Weekly Project Update
FUMC

Pat Tims
Aug 1, 2025
THIS WEEK'S ACCOMPLISHMENT
- Ash Masonry - Set Cor-1 Stone East Elevation
- ATC - Stripping, Cleaning South Elevation
- ATC - Applied Tints On Cor-4 Stone For Comparison
- Red River Restoration - Stripped Jambs, Lintels, S-302,303,304,305,306
- Red River Restoration - Finished Paint E-301,302,303,304,305
- Stanton Studios - Disassembling S-302,303,304,305

Red River Restoration Stripping Jambs South Elevation Level 3
NEXT WEEK'S ACTIVITIES
- Stanton Studios - Installation W-302,303, E-305
- Stanton Studios - Installs Protective Glass S-301,307,401,N-401
- Red River Restoration - Finish Jambs, Lintels S-302,303,304,305,306
- Ash Masonry - Remove Gutter Stone Southwest Elevation
- Ash Masonry - Repair Rafters Southwest Elevation

- ATC - Stripping, Cleaning West Elevation
Cor-4 Tint Comparisons

Ash Masonry Placing Cor-1 Stone East Elevation
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page