Weekly Project Update

FUMC

Placeholder

Pat Tims

Aug 1, 2025

THIS WEEK'S ACCOMPLISHMENT

    Ash Masonry - Set Cor-1 Stone East Elevation
    ATC - Stripping, Cleaning South Elevation
    ATC - Applied Tints On Cor-4 Stone For Comparison
    Red River Restoration - Stripped Jambs, Lintels, S-302,303,304,305,306
    Red River Restoration - Finished Paint E-301,302,303,304,305
    Stanton Studios - Disassembling S-302,303,304,305
Excavation 1.jpg

Red River Restoration Stripping Jambs South Elevation Level 3

NEXT WEEK'S ACTIVITIES

    Stanton Studios - Installation W-302,303, E-305
    Stanton Studios - Installs Protective Glass S-301,307,401,N-401
    Red River Restoration - Finish Jambs, Lintels S-302,303,304,305,306
    Ash Masonry - Remove Gutter Stone Southwest Elevation
    Ash Masonry - Repair Rafters Southwest Elevation
Excavation 1.jpg
    ATC - Stripping, Cleaning West Elevation

Cor-4 Tint Comparisons

Excavation 1.jpg

Ash Masonry Placing Cor-1 Stone East Elevation

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.