Weekly Project Update
FUMC

Pat Tims
Feb 13, 2026
THIS WEEK'S ACCOMPLISHMENT
- ATC - Added Additionl Coat of Sealer On E&D-1, E&D-2 West Elevation
- ATC - First Coat of Sealer South Elevation Completed
- Red River Restoration - W-303 Interior Repairs Completed
- Ash Masonry - Removed Cor-12 Stones, Set Three E&D-6 & Three Cor-12 Stones South Elevation
- Ash Masonry - Mortared E&D-6 & Cor-12 Stones South Elevation
- AGC Safety Inspection - 100% Pass

Final Sealing Finials South Elevation
NEXT WEEK'S ACTIVITIES
- ATC - Second Coat of Sealer E&D-1 & 2, Cor-17 Stones South Elevation
- Ash Masonry - Remove Cor-12 Stone
- Ash Masonry - Rafter Repairs Southwest Elevation
- Ash Masonry - Repair Gutter Box Southwest Elevation
- Ash Masonry - Set Remaining Cor-12 Stone

- Ash Masonry - Mortar Remaining Stones Southwest Elevation
ATC Sealing E&D-1 Stones South Elevation

E&D-6, Cor-12 Stones Set South Elevation
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.