Weekly Project Update

FUMC

Placeholder

Pat Tims

Feb 13, 2026

THIS WEEK'S ACCOMPLISHMENT

    ATC - Added Additionl Coat of Sealer On E&D-1, E&D-2 West Elevation
    ATC - First Coat of Sealer South Elevation Completed
    Red River Restoration - W-303 Interior Repairs Completed
    Ash Masonry - Removed Cor-12 Stones, Set Three E&D-6 & Three Cor-12 Stones South Elevation
    Ash Masonry - Mortared E&D-6 & Cor-12 Stones South Elevation
    AGC Safety Inspection - 100% Pass
Excavation 1.jpg

Final Sealing Finials South Elevation

NEXT WEEK'S ACTIVITIES

    ATC - Second Coat of Sealer E&D-1 & 2, Cor-17 Stones South Elevation
    Ash Masonry - Remove Cor-12 Stone
    Ash Masonry - Rafter Repairs Southwest Elevation
    Ash Masonry - Repair Gutter Box Southwest Elevation
    Ash Masonry - Set Remaining Cor-12 Stone
Excavation 1.jpg
    Ash Masonry - Mortar Remaining Stones Southwest Elevation

ATC Sealing E&D-1 Stones South Elevation

Excavation 1.jpg

E&D-6, Cor-12 Stones Set South Elevation

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.