THIS WEEK'S ACCOMPLISHMENT

    Ash Masonry - Removed Remaining Capitals West Elevation
    Ash Masonry - Repaired Two Columns West Elevation
    Ash Masonry - FYFE shipped CFRP
    Red River Restoration - Finished Sash Lock Installation
    Red River Restoration - Finished Final Touchup W-302, 303, 304, 305, 306, 307
    ATC - Cleaned Historical Limestone Finial
Excavation 1.jpg

Structural Repairs Columns West Elevation

NEXT WEEK'S ACTIVITIES

    Ash Masonry - Prep Columns For CFRP Installation
    Ash Masonry - Install CFRP Columns West Elevation
    Ash Masonry - Test Fit Corner Stone Mockups
    Advanced Architectural Stone - Gutter Stones Curing, Scheduled Arrival 1-19
    ATC - Finishes Sealing Limestone Finial For South Elevation
Excavation 1.jpg
    Ash Masonry - Sets Limestone Finial South Elevation

ATC - Cleaning Limestone Finial

Excavation 1.jpg

Column Capitals Removed West Elevation

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.