Weekly Project Update
FUMC

Pat Tims
Nov 7, 2025
THIS WEEK'S ACCOMPLISHMENT
- Ash Masonry - Set 7 Cor-4 Stones East Gable North Elevation
- Ash Masonry - Installed 48 Hurricane Clips
- Ash Masonry - Began Pointing South Elevation
- Stanton Studios - Installed Protective Frames S-303,304,305,306,307
- Stanton Studios - Continued Restoration N-303 80%, 304 60%, 305 55%, 306,307 20%
- Advanced Architectural Stone - Drawings Finishing For E&D-6,

Red River Restoration - Finishing Up S-305
NEXT WEEK'S ACTIVITIES
- Ash Masonry - Pointing Continues South Elevation
- Ash Masonry - Sets Remaining Cor-4 Stones East Gable North Elevation
- Red River Restoration - Finishes Hardware N-303,304,305,306,307. W-302,303 Hardware In Process.
- Stanton Studios - Continues Restoration N-303,304,305,306,307
- Advanced Architectural Stone - E&D Drawings For Review

- Advanced Architectural Stone - Detailing E&D Dutchman
Ash Masonry - Pointing South Elevation

Ash Masonry - Cor-4 Stones East Gable North Elevation
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.