Weekly Project Update

FUMC

Placeholder

Pat Tims

Nov 7, 2025

THIS WEEK'S ACCOMPLISHMENT

    Ash Masonry - Set 7 Cor-4 Stones East Gable North Elevation
    Ash Masonry - Installed 48 Hurricane Clips
    Ash Masonry - Began Pointing South Elevation
    Stanton Studios - Installed Protective Frames S-303,304,305,306,307
    Stanton Studios - Continued Restoration N-303 80%, 304 60%, 305 55%, 306,307 20%
    Advanced Architectural Stone - Drawings Finishing For E&D-6,
Excavation 1.jpg

Red River Restoration - Finishing Up S-305

NEXT WEEK'S ACTIVITIES

    Ash Masonry - Pointing Continues South Elevation
    Ash Masonry - Sets Remaining Cor-4 Stones East Gable North Elevation
    Red River Restoration - Finishes Hardware N-303,304,305,306,307. W-302,303 Hardware In Process.
    Stanton Studios - Continues Restoration N-303,304,305,306,307
    Advanced Architectural Stone - E&D Drawings For Review
Excavation 1.jpg
    Advanced Architectural Stone - Detailing E&D Dutchman

Ash Masonry - Pointing South Elevation

Excavation 1.jpg

Ash Masonry - Cor-4 Stones East Gable North Elevation

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.