top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

FUMC

Placeholder

Pat Tims

Sep 5, 2025

THIS WEEK'S ACCOMPLISHMENT

    Advanced Architectural Stone - Finials Onsite For The West Elevation
    Advanced Architectural Stone - Finials Are Cured & Ready For Shipping
    ATC - Nearing Completion East Elevation Stripping & Cleaning
    Ash Masonry - Removed Brick & Frieze Stone At The Southwest Elevation For An Improved Structural Connection
    Ash Masonry - Finish Prep For North Capital Repair
    Stanton Studios - S-302,303,304,305,306 Restoration Is 70-75% Complete
Excavation 1.jpg

Additional Water Proofing Installed Southwest Elevation

NEXT WEEK'S ACTIVITIES

    Ash Masonry - West Elevation Carpentry Repairs On Facia, & Installation Of Joist Hangers
    Ash Masonry - Finish Repairs On The Remaining North Capitals
    Lost Art Structures - Directive On Structural Connection Change
    ATC - Complete Stripping & Cleaning East Elevation
    Stanton Studios - Continues Restoration S-302,303,304,305,306; 85% Complete
Excavation 1.jpg

The Team Finding Solutions

Excavation 1.jpg

Ash Masonry - Brick & Frieze Stone Removed

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page