THIS WEEK'S ACCOMPLISHMENT
- Advanced Architectural Stone - Finials Onsite For The West Elevation
- Advanced Architectural Stone - Finials Are Cured & Ready For Shipping
- ATC - Nearing Completion East Elevation Stripping & Cleaning
- Ash Masonry - Removed Brick & Frieze Stone At The Southwest Elevation For An Improved Structural Connection
- Ash Masonry - Finish Prep For North Capital Repair
- Stanton Studios - S-302,303,304,305,306 Restoration Is 70-75% Complete

Additional Water Proofing Installed Southwest Elevation
NEXT WEEK'S ACTIVITIES
- Ash Masonry - West Elevation Carpentry Repairs On Facia, & Installation Of Joist Hangers
- Ash Masonry - Finish Repairs On The Remaining North Capitals
- Lost Art Structures - Directive On Structural Connection Change
- ATC - Complete Stripping & Cleaning East Elevation
- Stanton Studios - Continues Restoration S-302,303,304,305,306; 85% Complete

-