THIS WEEK'S ACCOMPLISHMENT
- Ash Masonry - Set 9 Cor-4 Stones North Elevation
- Ash Masonry - Removed E&D-1 Stone North Elevation To Be Replaced
- Ash Masonry - Set Finials 1B,1C South Elevation
- Ash Masonry - Pointed South Elevation
- Stanton Studios - N-303 95%, N-304 75%, N-305 70%, N-306 35%, N-307 35% Complete
- Burnish Finishes - Proposal Received W-302, 303, S-301, N-308

Ash Masonry - Pointing
NEXT WEEK'S ACTIVITIES
- Arc Abatement - Abate Bird Excrement
- Stanton Studio - N-303 100%, N-304 90%, N-305 85%, N-306 50%, N-307 50% Complete
- Ash Masonry - West Elevation Pointing Completed
- Ash Masonry - Sets Finials 1B, 1C, 1A
- Ash Masonry - Hurricane Clip Installation Completed

- Red River Restoration - Window Crank Restoration Complete N-304,305, 306, 307
Ash Masonry - Cor-4 Stones Set North Elevation

Finial Templates South Elevation