Weekly Project Update

FUMC

Placeholder

Pat Tims

Nov 14, 2025

THIS WEEK'S ACCOMPLISHMENT

    Ash Masonry - Set 9 Cor-4 Stones North Elevation
    Ash Masonry - Removed E&D-1 Stone North Elevation To Be Replaced
    Ash Masonry - Set Finials 1B,1C South Elevation
    Ash Masonry - Pointed South Elevation
    Stanton Studios - N-303 95%, N-304 75%, N-305 70%, N-306 35%, N-307 35% Complete
    Burnish Finishes - Proposal Received W-302, 303, S-301, N-308
Excavation 1.jpg

Ash Masonry - Pointing

NEXT WEEK'S ACTIVITIES

    Arc Abatement - Abate Bird Excrement
    Stanton Studio - N-303 100%, N-304 90%, N-305 85%, N-306 50%, N-307 50% Complete
    Ash Masonry - West Elevation Pointing Completed
    Ash Masonry - Sets Finials 1B, 1C, 1A
    Ash Masonry - Hurricane Clip Installation Completed
Excavation 1.jpg
    Red River Restoration - Window Crank Restoration Complete N-304,305, 306, 307

Ash Masonry - Cor-4 Stones Set North Elevation

Excavation 1.jpg

Finial Templates South Elevation

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.