Weekly Project Update

FUMC

Placeholder

Pat Tims

Aug 8, 2025

THIS WEEK'S ACCOMPLISHMENT

    Ash Masonry - Removed Cor-12,13 Gutter Stones
    Ash Masonry - Repaired North Capital For Approval
    Ash Masonry - Installed Hurricane Clips For Carpentry Repairs
    Red River Restoration - Removed Rust Primes & Painted Lintels
    Red River - Primed & Painted S-302,303,304,305,306
    Stanton Studios - Installed Protective Glass N-301,401, S-301,401
Excavation 1.jpg

Brain O'Keefe Of Red River Restoration Preparing Jambs South Elevation

NEXT WEEK'S ACTIVITIES

    Stanton Studios - Install W-302,303, E-301,305 Sashes
    Stanton Studios - Install Frames S-302,303,304,305,306
    Stanton Studios - Restoration Process Continues S-302,303,304,305,306
    Ash Masonry - Repair Rafters Southwest Elevation
    Ash Masonry - Repair North Capitals
Excavation 1.jpg
    ATC - Apply Tint/Sealer South Elevation For Comparison To Columns.

Forrest Pope Preparation For Capital Repair

Excavation 1.jpg

Forrest Pope Repairing North Capital

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.