top of page


Weekly Project Update
FUMC

Pat Tims
Aug 8, 2025
THIS WEEK'S ACCOMPLISHMENT
- Ash Masonry - Removed Cor-12,13 Gutter Stones
- Ash Masonry - Repaired North Capital For Approval
- Ash Masonry - Installed Hurricane Clips For Carpentry Repairs
- Red River Restoration - Removed Rust Primes & Painted Lintels
- Red River - Primed & Painted S-302,303,304,305,306
- Stanton Studios - Installed Protective Glass N-301,401, S-301,401

Brain O'Keefe Of Red River Restoration Preparing Jambs South Elevation
NEXT WEEK'S ACTIVITIES
- Stanton Studios - Install W-302,303, E-301,305 Sashes
- Stanton Studios - Install Frames S-302,303,304,305,306
- Stanton Studios - Restoration Process Continues S-302,303,304,305,306
- Ash Masonry - Repair Rafters Southwest Elevation
- Ash Masonry - Repair North Capitals

- ATC - Apply Tint/Sealer South Elevation For Comparison To Columns.
Forrest Pope Preparation For Capital Repair

Forrest Pope Repairing North Capital
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page