Weekly Project Update
FUMC

Pat Tims
Jul 18, 2025
THIS WEEK'S ACCOMPLISHMENT
- Ash Masonry - Removed E&D-5, Cor-19, Cor-18 South Elevation
- Ash Masonry - Pointed Sill Stones South Elevation
- Stanton Studios - Installed S-301, E-301,302,303,304,305
- Stanton Studios - Removed S-302,303,304,305,306
- Advanced Architectural Stone - Cor-1,2,3 Stones Curing
- Delivered Cor-16 OH & Egg & Dart 5 To Advanced Architectural Stone For Molding

Stanton Studios - E-304 Installed
NEXT WEEK'S ACTIVITIES
- Ash Masonry - Remove Cor-9, 11 Stones
- Ash Masonry - Point East, West Sill Stones
- Stanton Studios - Repair Sash E-301, Install Glass In Sash E-305
- Stanton Studios - Complete Restoration W-302,303
- Arc Abatement - Abate S-302,303,304,305,306

- Red River Restoration - Strip, Remove Rust, Prime S-302,303,304,305,306
Ash Masonry - Removing Cor-19

Advanced Architectural Stone - Preparing Clam Shell For Molding
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.