Weekly Project Update

FUMC

Placeholder

Pat Tims

Jul 18, 2025

THIS WEEK'S ACCOMPLISHMENT

    Ash Masonry - Removed E&D-5, Cor-19, Cor-18 South Elevation
    Ash Masonry - Pointed Sill Stones South Elevation
    Stanton Studios - Installed S-301, E-301,302,303,304,305
    Stanton Studios - Removed S-302,303,304,305,306
    Advanced Architectural Stone - Cor-1,2,3 Stones Curing
    Delivered Cor-16 OH & Egg & Dart 5 To Advanced Architectural Stone For Molding
Excavation 1.jpg

Stanton Studios - E-304 Installed

NEXT WEEK'S ACTIVITIES

    Ash Masonry - Remove Cor-9, 11 Stones
    Ash Masonry - Point East, West Sill Stones
    Stanton Studios - Repair Sash E-301, Install Glass In Sash E-305
    Stanton Studios - Complete Restoration W-302,303
    Arc Abatement - Abate S-302,303,304,305,306
Excavation 1.jpg
    Red River Restoration - Strip, Remove Rust, Prime S-302,303,304,305,306

Ash Masonry - Removing Cor-19

Excavation 1.jpg

Advanced Architectural Stone - Preparing Clam Shell For Molding

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.