Weekly Project Update

FUMC

Placeholder

Pat Tims

Jul 11, 2025

THIS WEEK'S ACCOMPLISHMENT

    ATC - Onsite Stripping Paint, Cleaning Stones South Elevation
    Ash Masonry - Removed Cor-16 OH, Cor-19 Transition Stone South Elevation
    Ash Masonry - Mortared Cor-4 Stones West & South Elevations
    Stanton Studios - Installed Protective Glass N-301,
    Stanton Studios - E-301,302,303,304,305 95% Complete For Installation 7-17
    Advanced Architectural Stone - Produced Beautiful Finial -1B Stone
Excavation 1.jpg

ATC - Removing Paint & Washing Egg & Dart Stones South Elevaiton

NEXT WEEK'S ACTIVITIES

    Curb Cut Onsite To Remove Stones
    Ash Masonry - Removes Stones To Deliver Stones To Advanced Architectural Stone
    ATC - Continues Stripping, Cleaning South Elevation
    Red River Restoration - Installs Hardware
    Stanton Studios - Installs E-301,302,303,304,305
Excavation 1.jpg
    Braun & Butler Delivers Stones To Advanced Architectural Stone

Stanton Studios Installing/Cleaning Protective Glass S-308

Excavation 1.jpg

Advanced Architectural Stones New Finial-1 B

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.