top of page


Weekly Project Update
FUMC

Pat Tims
Jul 11, 2025
THIS WEEK'S ACCOMPLISHMENT
- ATC - Onsite Stripping Paint, Cleaning Stones South Elevation
- Ash Masonry - Removed Cor-16 OH, Cor-19 Transition Stone South Elevation
- Ash Masonry - Mortared Cor-4 Stones West & South Elevations
- Stanton Studios - Installed Protective Glass N-301,
- Stanton Studios - E-301,302,303,304,305 95% Complete For Installation 7-17
- Advanced Architectural Stone - Produced Beautiful Finial -1B Stone

ATC - Removing Paint & Washing Egg & Dart Stones South Elevaiton
NEXT WEEK'S ACTIVITIES
- Curb Cut Onsite To Remove Stones
- Ash Masonry - Removes Stones To Deliver Stones To Advanced Architectural Stone
- ATC - Continues Stripping, Cleaning South Elevation
- Red River Restoration - Installs Hardware
- Stanton Studios - Installs E-301,302,303,304,305

- Braun & Butler Delivers Stones To Advanced Architectural Stone
Stanton Studios Installing/Cleaning Protective Glass S-308

Advanced Architectural Stones New Finial-1 B
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page