THIS WEEK'S ACCOMPLISHMENT

    Ash Masonry - Mortared Finial Stones South Elevation
    Ash Masonry - Pointed South Elevation
    Ash Masonry - Mortared Cor-4 Stones North Elevation East Gable
    Ash Masonry - Installed Rafter Clips
    Stanton Studios - Installed Protective Glass South Elevation Sanctuary Windows
    Stanton Studios - Restoration Continues North Elevation Sanctuary Windows; Two Scheduled Installation 12-9, Remaining Three 12-19
Excavation 1.jpg

Ash Masonry - Mortaring Cor-4 Stones North Elevation

NEXT WEEK'S ACTIVITIES

    Ash Masonry - Pointing, Grouting Cor-4 Stones North Elevation
    Ash Masonry - Rafter Clip Installation Completed
    Ash Masonry - Pointing East Elevation
    Arc Abatement - Remove Bird Excrement
    Stanton Studios - Restoration Continues Remaining Sanctuary Windows
Excavation 1.jpg
    Red River Restoration - Hardware Restoration W-302,303 Cranks Completed

Ash Masonry - Pointing North Elevaiton

Excavation 1.jpg

Stanton Studios - South Sanctuary Protective Glass Installation Completed

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.