THIS WEEK'S ACCOMPLISHMENT
- Ash Masonry - Mortared Finial Stones South Elevation
- Ash Masonry - Pointed South Elevation
- Ash Masonry - Mortared Cor-4 Stones North Elevation East Gable
- Ash Masonry - Installed Rafter Clips
- Stanton Studios - Installed Protective Glass South Elevation Sanctuary Windows
- Stanton Studios - Restoration Continues North Elevation Sanctuary Windows; Two Scheduled Installation 12-9, Remaining Three 12-19

Ash Masonry - Mortaring Cor-4 Stones North Elevation
NEXT WEEK'S ACTIVITIES
- Ash Masonry - Pointing, Grouting Cor-4 Stones North Elevation
- Ash Masonry - Rafter Clip Installation Completed
- Ash Masonry - Pointing East Elevation
- Arc Abatement - Remove Bird Excrement
- Stanton Studios - Restoration Continues Remaining Sanctuary Windows

- Red River Restoration - Hardware Restoration W-302,303 Cranks Completed
Ash Masonry - Pointing North Elevaiton

Stanton Studios - South Sanctuary Protective Glass Installation Completed