Weekly Project Update

FUMC

Placeholder

Pat Tims

Aug 15, 2025

THIS WEEK'S ACCOMPLISHMENT

    ATC - Removed Paint & Cleaned The West Elevation
    ATC - Applied Tinted Sealer Sample
    Heimsath Architects Approve Color For Sealer & Tint
    Stanton Studios - Installed E-301,305, W-302,303
    Ash Masonry - Removed Frieze Stone Above Capital West Elevation
    Cor - 11,12,13,19, Stones Shipped To Advanced Architectural Stone
Excavation 1.jpg

ATC - Removing & Washing West Elevation

NEXT WEEK'S ACTIVITIES

    Stanton Studios - Restoration Continues S-302,303,304,305,306
    Stanton Studios - Installing Protective Glass W-302,303,
    ATC - Paint Removal North Elevation
    Ash Masonry - Set Cor-2,3 East Elevation
    Ash Masonry - Repairs North Capital
Excavation 1.jpg
    Ash Masonry Completes Rafter Repairs Southwest Elevation

Frieze Stone Removal West Elevation

Excavation 1.jpg

Tinted Sealer Applied South Elevation

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.