top of page


Weekly Project Update
FUMC

Pat Tims
Aug 15, 2025
THIS WEEK'S ACCOMPLISHMENT
- ATC - Removed Paint & Cleaned The West Elevation
- ATC - Applied Tinted Sealer Sample
- Heimsath Architects Approve Color For Sealer & Tint
- Stanton Studios - Installed E-301,305, W-302,303
- Ash Masonry - Removed Frieze Stone Above Capital West Elevation
- Cor - 11,12,13,19, Stones Shipped To Advanced Architectural Stone

ATC - Removing & Washing West Elevation
NEXT WEEK'S ACTIVITIES
- Stanton Studios - Restoration Continues S-302,303,304,305,306
- Stanton Studios - Installing Protective Glass W-302,303,
- ATC - Paint Removal North Elevation
- Ash Masonry - Set Cor-2,3 East Elevation
- Ash Masonry - Repairs North Capital

- Ash Masonry Completes Rafter Repairs Southwest Elevation
Frieze Stone Removal West Elevation

Tinted Sealer Applied South Elevation
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page