Weekly Project Update

FUMC

Placeholder

Pat Tims

Oct 10, 2025

THIS WEEK'S ACCOMPLISHMENT

    Ash Masonry - Removed E&D Southwest Elevation
    Ash Masonry - Pointed South Elevation
    THC - Sealer Approved
    Advanced Architectural Stone - Gutter Stones In Production
    Red River Restoration - Hardware Restoration Completed Level 4
    Stanton Studios - 95% Complete Sanctuary Windows South Elevation
Excavation 1.jpg

Red River Restoration South Elevation

NEXT WEEK'S ACTIVITIES

    Stanton Studios - Installation Two Sanctuary Windows South Elevation 10-13
    Ash Masonry - Complete Pointing West Elevation
    Ash Masonry - Remove Cor-4 Stones West Gable North Elevation
    Ash Masonry - Set Cor-4 Stones West Gable North Elevation
    ATC - Clean & Tint Columns East, South Elevation
Excavation 1.jpg
    CMP - Structural Connection Southwest, Northwest Elevation

Jeff Rubino Inspecting West Elevation

Excavation 1.jpg

Empire Temporary Roofing North Elevation West Gable

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.