Weekly Project Update
FUMC

Pat Tims
Oct 3, 2025
THIS WEEK'S ACCOMPLISHMENT
- Ash Masonry - North Capital Repairs Completed
- Ash Masonry - Finished Roof Carpentry Work East Elevation
- Ash Masonry - Removed Egg & Dart 6 South Elevaiton
- Ash Masonry - Removed Remaining Concrete Capital Column West Elevation
- Red River Restoration - N-303 Repaired & Primed
- Red River Restoration - Additional Repairs, Paint S-302,304,305,306

Ash Masonry Cor-14 Removed, Egg & Dart 6 To Follow
NEXT WEEK'S ACTIVITIES
- Lost Art Structures Zach Webb - Directive Egg & Dart Repairs West
- Lost Art Structures Zach Webb - Directive North Capital Repair
- Red River Restoration - Install Hardware, Sanctuary & Balcony Windows
- Stanton Studios - Install Two South Elevation Sanctuary Windows
- Stanton Studios - Remove Two North Elevation Sanctuary Windows

- Stanton Studios - Continue Restoration South Elevation Sanctuary Windows
Red River Restoration - N-303

Ash Masonry - Repairing North Capital
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.