Weekly Project Update

FUMC

Placeholder

Pat Tims

Oct 3, 2025

THIS WEEK'S ACCOMPLISHMENT

    Ash Masonry - North Capital Repairs Completed
    Ash Masonry - Finished Roof Carpentry Work East Elevation
    Ash Masonry - Removed Egg & Dart 6 South Elevaiton
    Ash Masonry - Removed Remaining Concrete Capital Column West Elevation
    Red River Restoration - N-303 Repaired & Primed
    Red River Restoration - Additional Repairs, Paint S-302,304,305,306
Excavation 1.jpg

Ash Masonry Cor-14 Removed, Egg & Dart 6 To Follow

NEXT WEEK'S ACTIVITIES

    Lost Art Structures Zach Webb - Directive Egg & Dart Repairs West
    Lost Art Structures Zach Webb - Directive North Capital Repair
    Red River Restoration - Install Hardware, Sanctuary & Balcony Windows
    Stanton Studios - Install Two South Elevation Sanctuary Windows
    Stanton Studios - Remove Two North Elevation Sanctuary Windows
Excavation 1.jpg
    Stanton Studios - Continue Restoration South Elevation Sanctuary Windows

Red River Restoration - N-303

Excavation 1.jpg

Ash Masonry - Repairing North Capital

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.