Weekly Project Update

FUMC

Placeholder

Pat Tims

Sep 26, 2025

THIS WEEK'S ACCOMPLISHMENT

    Ash Masonry - Roof Deck Repairs 95% Complete
    Ash Masonry - Mortar Wash West Elevation Pediment Complete, Mortar Wash South Elevation Completion 9-29
    Stanton Studios - Installed S-303, Removed N-303, Stained Interior N-308
    ATC - Finished Stripping & Washing North Elevation
    ATC - Cleaned Cor-1,2,3, & Cor-4 Stones West Elevation
    CMP - S2.0 Detail 4 Framing-To-Stone Connection Shop Drawings In Process
Excavation 1.jpg

ATC - Final Wash North Elevation Level 4

NEXT WEEK'S ACTIVITIES

    Stanton Studios - Restoration Process, Two Windows Scheduled Installation 10-9
    ATC - Applies Clear Coat Sample
    ATC - Pending THC Approval, Coating Applied On Cor-4 West Elevation
    Ash Masonry - Finish North Capitals Repairs
    Ash Masonry - Remove E&D Stones Per Directive
Excavation 1.jpg
    Red River Restoration - Install Trim, Repair Sash, Finish Coat S-303

Ash Masonry - Installing Sheathing

Excavation 1.jpg

Ash Masonry - Prepping North Capital

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.