Weekly Project Update
FUMC

Pat Tims
Sep 26, 2025
THIS WEEK'S ACCOMPLISHMENT
- Ash Masonry - Roof Deck Repairs 95% Complete
- Ash Masonry - Mortar Wash West Elevation Pediment Complete, Mortar Wash South Elevation Completion 9-29
- Stanton Studios - Installed S-303, Removed N-303, Stained Interior N-308
- ATC - Finished Stripping & Washing North Elevation
- ATC - Cleaned Cor-1,2,3, & Cor-4 Stones West Elevation
- CMP - S2.0 Detail 4 Framing-To-Stone Connection Shop Drawings In Process

ATC - Final Wash North Elevation Level 4
NEXT WEEK'S ACTIVITIES
- Stanton Studios - Restoration Process, Two Windows Scheduled Installation 10-9
- ATC - Applies Clear Coat Sample
- ATC - Pending THC Approval, Coating Applied On Cor-4 West Elevation
- Ash Masonry - Finish North Capitals Repairs
- Ash Masonry - Remove E&D Stones Per Directive

- Red River Restoration - Install Trim, Repair Sash, Finish Coat S-303
Ash Masonry - Installing Sheathing

Ash Masonry - Prepping North Capital