Weekly Project Update
FUMC

Pat Tims
Dec 19, 2025
THIS WEEK'S ACCOMPLISHMENT
- Ash Masonry - Completed Clam Shell Installation West & South Elevations
- Ash Masonry - Completed Mock-up Cor-7OH Form
- Stanton Studios - Installed Remaining Three Sanctuary Windows
- Advanced Architectural Stone - Gutter Stones Shipping First Week In January
- Advanced Architectural Stone - GFRC Approved For Corner Stones
- Red River Restoration - Repairs Complete N-304, N-305

Finial In Place
NEXT WEEK'S ACTIVITIES
- Burnish Finishes - Completes Repairs & Painting W-302, W-303
- Stanton Studios - Installs N-203
- Stanton Studios - Installs Protective Frames Three Sanctuary Windows North Elevation
- Stanton Studios - Installs Protective Frame Interior Family Room Window
- Advanced Architectural Stone - Designs GFRC Corner Stones

- MERRY CHRISTMAS & BLESSINGS TO ALL!
North Elevation Sanctuary Windows Installed

Christmas Time
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.