Weekly Project Update

FUMC

Placeholder

Pat Tims

Dec 19, 2025

THIS WEEK'S ACCOMPLISHMENT

    Ash Masonry - Completed Clam Shell Installation West & South Elevations
    Ash Masonry - Completed Mock-up Cor-7OH Form
    Stanton Studios - Installed Remaining Three Sanctuary Windows
    Advanced Architectural Stone - Gutter Stones Shipping First Week In January
    Advanced Architectural Stone - GFRC Approved For Corner Stones
    Red River Restoration - Repairs Complete N-304, N-305
Excavation 1.jpg

Finial In Place

NEXT WEEK'S ACTIVITIES

    Burnish Finishes - Completes Repairs & Painting W-302, W-303
    Stanton Studios - Installs N-203
    Stanton Studios - Installs Protective Frames Three Sanctuary Windows North Elevation
    Stanton Studios - Installs Protective Frame Interior Family Room Window
    Advanced Architectural Stone - Designs GFRC Corner Stones
Excavation 1.jpg
    MERRY CHRISTMAS & BLESSINGS TO ALL!

North Elevation Sanctuary Windows Installed

Excavation 1.jpg

Christmas Time

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.