Weekly Project Update

Good Shepherd Organ Platform 06/27/2025

Placeholder

Steven Conrad

Jun 27, 2025

THIS WEEK'S ACCOMPLISHMENT

    Completed demo work of the existing concrete and ladder up to the 4th floor (Belfry Tower)
Excavation 1.jpg

Existing scuttle hole enlarged and ladder removed

NEXT WEEK'S ACTIVITIES

    Salvage existing roof shingles and weather proof exterior roof
    Start the demo of the existing stone on the exterior of the bell tower
    Install the lintel and C-Channel steel on the exterior of the bell tower
Excavation 1.jpg

Exterior bell tower where lintel will be installed

Excavation 1.jpg

Existing condition of bell tower

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.