Weekly Project Update
Good Shepherd Organ Platform 06/27/2025

Steven Conrad
Jun 27, 2025
THIS WEEK'S ACCOMPLISHMENT
- Completed demo work of the existing concrete and ladder up to the 4th floor (Belfry Tower)
-
-
-
-
-

Existing scuttle hole enlarged and ladder removed
NEXT WEEK'S ACTIVITIES
- Salvage existing roof shingles and weather proof exterior roof
- Start the demo of the existing stone on the exterior of the bell tower
- Install the lintel and C-Channel steel on the exterior of the bell tower
-
-

-
Exterior bell tower where lintel will be installed

Existing condition of bell tower
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.