Weekly Project Update

Good Shepherd Organ Platform 07/03/2025

Placeholder

Steven Conrad

Jul 3, 2025

THIS WEEK'S ACCOMPLISHMENT

    Removed and salvaged existing roof shingles
    Applied waterproof barrier to exposed roof
Excavation 1.jpg

NEXT WEEK'S ACTIVITIES

    Install masonry support lintel
    Start removing exterior masonry
Excavation 1.jpg

Excavation 1.jpg

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.