Weekly Project Update

Good Shepherd Organ Platform 07/11/2025

Placeholder

Steven Conrad

Jul 11, 2025

THIS WEEK'S ACCOMPLISHMENT

    Installed exterior lintel for overhead masonry support
Excavation 1.jpg

Installed Lintel and protected from the weather

NEXT WEEK'S ACTIVITIES

    Grout fill clay tile to receive anchor bolts for structural support for new roof
    Start erecting new roof parapet walls
Excavation 1.jpg

Areas to receive grout for anchors for the structural members

Excavation 1.jpg

Area of new roof to be erected

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.