top of page


Weekly Project Update
Good Shepherd Organ Platform 08/01/2025

Steven Conrad
Aug 1, 2025
THIS WEEK'S ACCOMPLISHMENT
- Install C-Channel for new roof support
- Start demo on interior of bell tower clay tile wall
- Infill windows internally with CMU block
- Install structural steel for roof support
- Erect roof 3 and wall 4
- Dry in new portion of new roof

New section of roof as seen from inside the church
NEXT WEEK'S ACTIVITIES
- Install TPO and roof shingles
- Open the side of the bell tower for future organ pipes
- Build the blower room floor and walls
-
-

-
Bell tower wall to be demoed

New roof to receive TPO and shingles
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.