THIS WEEK'S ACCOMPLISHMENT

    Install C-Channel for new roof support
    Start demo on interior of bell tower clay tile wall
    Infill windows internally with CMU block
    Install structural steel for roof support
    Erect roof 3 and wall 4
    Dry in new portion of new roof
Excavation 1.jpg

New section of roof as seen from inside the church

NEXT WEEK'S ACTIVITIES

    Install TPO and roof shingles
    Open the side of the bell tower for future organ pipes
    Build the blower room floor and walls
Excavation 1.jpg

Bell tower wall to be demoed

Excavation 1.jpg

New roof to receive TPO and shingles