top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

Good Shepherd Organ Platform 08/15/2025

Placeholder

Steven Conrad

Aug 15, 2025

THIS WEEK'S ACCOMPLISHMENT

    Infilled both windows on the bell tower
    Started to reinstall the salvaged shingles onto the roof
Excavation 1.jpg

Windsor Rd window infilled with salvaged stone

NEXT WEEK'S ACTIVITIES

    Finish installing shingles on new roof
    Install structural steel for the organ platforms
Excavation 1.jpg

Shingles currently getting reinstalled on the roof

Excavation 1.jpg

New organ opening awaiting structural steel for organ platform

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page