THIS WEEK'S ACCOMPLISHMENT
- Infilled both windows on the bell tower
- Started to reinstall the salvaged shingles onto the roof
-
-
-
-

Windsor Rd window infilled with salvaged stone
NEXT WEEK'S ACTIVITIES
- Finish installing shingles on new roof
- Install structural steel for the organ platforms
-
-
-

-
Shingles currently getting reinstalled on the roof

New organ opening awaiting structural steel for organ platform