Weekly Project Update

Good Shepherd Organ Platform 08/29/2025

Placeholder

Steven Conrad

Aug 29, 2025

THIS WEEK'S ACCOMPLISHMENT

    Started installing new tongue and groove boards on the new ceilings
    Completed some masonry patchwork on the concrete beams in the belltower walls
    Repaired the stucco finish above the choir stage
Excavation 1.jpg

NEXT WEEK'S ACTIVITIES

    Finish installing the new tongue and groove boards on the new ceilings and walls
Excavation 1.jpg

Excavation 1.jpg

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.