THIS WEEK'S ACCOMPLISHMENT
- Installed tongue & groove boards on the new ceiling above the sanctuary side
- Installed tongue & groove boards on the new ceiling above the stage side
- Installed tongue & groove boards on the new walls above the stage side
-
-
-

NEXT WEEK'S ACTIVITIES
- Finish installing tongue and groove boards
- Install the new ladder up to the Belfry
-
-
-

-