Weekly Project Update

Good Shepherd Organ Platform 09/05/2025

Placeholder

Steven Conrad

Sep 5, 2025

THIS WEEK'S ACCOMPLISHMENT

    Installed tongue & groove boards on the new ceiling above the sanctuary side
    Installed tongue & groove boards on the new ceiling above the stage side
    Installed tongue & groove boards on the new walls above the stage side
Excavation 1.jpg

NEXT WEEK'S ACTIVITIES

    Finish installing tongue and groove boards
    Install the new ladder up to the Belfry
Excavation 1.jpg

Excavation 1.jpg

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.