top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

Good Shepherd Organ Platform 09/05/2025

Placeholder

Steven Conrad

Sep 12, 2025

THIS WEEK'S ACCOMPLISHMENT

    Continued the installation of the new and salvaged tongue and groove boards on the new ceilings and walls
    Installed the stainless steel rods for the organ platform support
    Installed the new ladder extending up to the belfry
    Installed the structural steel column support for the blower room floor
    Installed the sound door on the blower room
    Installed framing around the organ platforms for the installation for tongue and groove boards for temporary walls until the organ is delivered and installed
Excavation 1.jpg

NEXT WEEK'S ACTIVITIES

    Finish installing the tongue and groove boards
    Demo the temp wall that was installed at the beginning of the job to separate the church from the project site
    Demo the floor and stage protection that was installed
    Prep for painters
Excavation 1.jpg

Excavation 1.jpg

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page