Weekly Project Update
Good Shepherd Organ Platform 09/05/2025

Steven Conrad
Sep 12, 2025
THIS WEEK'S ACCOMPLISHMENT
- Continued the installation of the new and salvaged tongue and groove boards on the new ceilings and walls
- Installed the stainless steel rods for the organ platform support
- Installed the new ladder extending up to the belfry
- Installed the structural steel column support for the blower room floor
- Installed the sound door on the blower room
- Installed framing around the organ platforms for the installation for tongue and groove boards for temporary walls until the organ is delivered and installed

NEXT WEEK'S ACTIVITIES
- Finish installing the tongue and groove boards
- Demo the temp wall that was installed at the beginning of the job to separate the church from the project site
- Demo the floor and stage protection that was installed
- Prep for painters
-

-

LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.