Weekly Project Update
Good Shepherd Organ Platform 09/19/2025

Steven Conrad
Sep 19, 2025
THIS WEEK'S ACCOMPLISHMENT
- Completed the install of all tongue and groove boards on new ceiling and walls
- Demoed the temp wall
- Demoed the flooring protection on the stage
- Removed the plastic protection for the existing organ pipes
- Reinstalled the choir pews on the stage
-

NEXT WEEK'S ACTIVITIES
- Final paint for the sanctuary and stage side of the original scope of work
- Demo the ceiling of the belltower entry room
- Reroute the HVAC condensate lines
- Reroute the fire and smoke alarm cables
- Reinstall Ceiling in the belltower entry room

-

LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.