Weekly Project Update

Good Shepherd Organ Platform 09/19/2025

Placeholder

Steven Conrad

Sep 22, 2025

THIS WEEK'S ACCOMPLISHMENT

    Completed the install of all tongue and groove boards on new ceiling and walls
    Demoed the temp wall
    Demoed the flooring protection on the stage
    Removed the plastic protection for the existing organ pipes
    Reinstalled the choir pews on the stage
Excavation 1.jpg

NEXT WEEK'S ACTIVITIES

    Final paint for the sanctuary and stage side of the original scope of work
Excavation 1.jpg

Excavation 1.jpg

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.