top of page


Weekly Project Update
Good Shepherd Organ Platform 09/19/2025

Steven Conrad
Sep 22, 2025
THIS WEEK'S ACCOMPLISHMENT
- Completed the install of all tongue and groove boards on new ceiling and walls
- Demoed the temp wall
- Demoed the flooring protection on the stage
- Removed the plastic protection for the existing organ pipes
- Reinstalled the choir pews on the stage
-

NEXT WEEK'S ACTIVITIES
- Final paint for the sanctuary and stage side of the original scope of work
-
-
-
-

-

LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page