Weekly Project Update

Griffith and Paseo

Placeholder

Ian Doyle

Aug 11, 2025

THIS WEEK'S ACCOMPLISHMENT

    Finished Framing West Balcony for Wood Soffit
    Finished Placing East Parking Lot Concrete Paving
    Finished Installing Brass Tap Fence Framing and Panels
    Finished Installing Irrigation Meter Water Connection
    Started Forming and Reinforcing for Paseo Etched Concrete #1
    Started Installing Level 1 Lobby Accoustibuilt Hard Lid Ceiling
Excavation 1.jpg

Irrigation Water Meter Supply Line Being Tapped

NEXT WEEK'S ACTIVITIES

    Finish Installing Brass Tap Fence and Placing Concrete Sidewalk
    Finish Forming and Reinforcing for Paseo Etched Concrete #1
    Finish Placing Paseo Etched Concrete #1
    Continue Installing Level 1 Lobby Accoustibuilt Hard Lid Ceiling
    Start Installing Visitor Center Wood Soffit Ceiling
Excavation 1.jpg
    Start Painting Exterior Paseo Canopies

East Parking Lot Concrete Pavement

Excavation 1.jpg

Installing Concrete Formwork for Paseo Etched Concrete Paving

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.