Weekly Project Update
Griffith and Paseo

Ian Doyle
Aug 11, 2025
THIS WEEK'S ACCOMPLISHMENT
- Finished Framing West Balcony for Wood Soffit
- Finished Placing East Parking Lot Concrete Paving
- Finished Installing Brass Tap Fence Framing and Panels
- Finished Installing Irrigation Meter Water Connection
- Started Forming and Reinforcing for Paseo Etched Concrete #1
- Started Installing Level 1 Lobby Accoustibuilt Hard Lid Ceiling

Irrigation Water Meter Supply Line Being Tapped
NEXT WEEK'S ACTIVITIES
- Finish Installing Brass Tap Fence and Placing Concrete Sidewalk
- Finish Forming and Reinforcing for Paseo Etched Concrete #1
- Finish Placing Paseo Etched Concrete #1
- Continue Installing Level 1 Lobby Accoustibuilt Hard Lid Ceiling
- Start Installing Visitor Center Wood Soffit Ceiling

- Start Painting Exterior Paseo Canopies
East Parking Lot Concrete Pavement

Installing Concrete Formwork for Paseo Etched Concrete Paving
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.