Weekly Project Update

Griffith and Paseo

Placeholder

Ian Doyle

Aug 4, 2025

THIS WEEK'S ACCOMPLISHMENT

    Finished Concrete Forming and Reinforcing East Parking Lot Paving
    Finished Installing Stone Masonry Around 1979 Windows
    Finished South Balcony Wood Soffit
    Continued Installing Storefront Windows
    Continued Framing West Balcony Wood Soffit
    Started Installing Brass Tap Fence
Excavation 1.jpg

South Balcony Wood Soffit

NEXT WEEK'S ACTIVITIES

    Finish Installing Brass Tap Fence
    Finish Framing West Balcony Wood Soffit
    Finish Placing East Parking Lot Concrete Paving
    Continue HVAC Start Up
    Start Installing Ceramic Floor Tile
Excavation 1.jpg
    Continue Installing Storefront Windows

Installation of Brass Tap Fence

Excavation 1.jpg

East Parking Lot Concrete Forming and Reinforcing

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.