Weekly Project Update
Griffith and Paseo

Ian Doyle
Jul 21, 2025
THIS WEEK'S ACCOMPLISHMENT
- Finished Site Work on East Parking Lot
- Finished Site Work on West Paseo
- Finished Weatherproofing 1979 Window Replacement Lintels
- Continued Installing Storefront Windows
- Started Installing Stone Masonry Around 1979 Window Openings
-

Flex Room Conversion to Offices Drywall Installation
NEXT WEEK'S ACTIVITIES
- Continue Installing Grid Ceiling in Chamber of Commerce
- Continue Installing Storefront Windows
- Continue Installing Stone Masonry Around 1979 Window Openings
- Start Laying out and Forming East Parking Lot Curbs
- Start Installing Brass Tap Fence Posts

-
Stone Masonry Installed Around South 1979 Window Openings

Completed Site Work on West Paseo Side
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.