top of page


Weekly Project Update
Griffith and Paseo

Ian Doyle
Jul 14, 2025
THIS WEEK'S ACCOMPLISHMENT
- Finished Installing Storefront Frames
- Finished Installing Bathroom Plumbing Fixtures Level 1 and 2
- Finished Installing Lights in Chamber of Commerce Area
- Continued Installing and Powering Lights
- Continued Weatherproofing 1979 Window Replacement Lintels
- Started Site Work on East Parking Lot and West Paseo Side

East Parking Lot Site Work
NEXT WEEK'S ACTIVITIES
- Finish Site Work on East Parking Lot
- Finish Weatherproofing 1979 Window Replacement Lintels
- Continue Installing Storefront Windows
- Continue Site Work on West Paseo Side
- Start Installing Stone Masonry Around 1979 Windows

- Start Installing Brass Tap Fence Posts
Visitor Center Storefront Window Installation

West Paseo Site Work Around Large Middle Canopy