Weekly Project Update
Griffith and Paseo

Ian Doyle
Aug 25, 2025
THIS WEEK'S ACCOMPLISHMENT
- Finished Painting Brass Tap Fence and Installing Hardware
- Finished Forming and Reinforcing for Paseo Stamped Concrete #1
- Finished Placing Paseo Stamped Concrete #1
- Continued Installing Paseo Underground Electrical
- Continued Installing Ceramic Tiles
- Started Installing Carpet Tiles

Brass Tap Fence Nears Completion
NEXT WEEK'S ACTIVITIES
- Finish Installing Paseo Underground Electrical
- Finish Forming and Reinforcing for Paseo Stage Concrete
- Finish Placing Paseo Stage Concrete
- Continue Installing Ceramic Tiles
- Continue Installing Carpet Tiles

-
Paseo Stamped Concrete #1

Ceramic Tile Installation on Level 2
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.