Weekly Project Update

Griffith and Paseo

Placeholder

Ian Doyle

Aug 19, 2025

THIS WEEK'S ACCOMPLISHMENT

    Finished Painting Exterior Paseo Canopies
    Finished Installing Brass Tap Fence and Placing Concrete Sidewalk
    Finished Forming and Reinforcing for Paseo Etched Concrete #1
    Finished Placing for Paseo Etched Concrete #1
    Continued Installing Level 1Lobby Accoustibuilt Hard Lid Ceiling
    Started Installing Millwork
Excavation 1.jpg

Millwork Installation

NEXT WEEK'S ACTIVITIES

    Finish Painting Brass Tap Fence and Installing Hardware
    Finish Forming and Reinforcing for Paseo Stamped Concrete #1
    Finish Placing for Paseo Stamped Concrete #1
    Continue Installing Paseo Underground Electrical
    Continue Installing Millwork
Excavation 1.jpg

Level 1 Lobby Accoustibuilt

Excavation 1.jpg

Paseo Etched Concrete #1 Placement