Weekly Project Update
Griffith and Paseo

Ian Doyle
Aug 19, 2025
THIS WEEK'S ACCOMPLISHMENT
- Finished Painting Exterior Paseo Canopies
- Finished Installing Brass Tap Fence and Placing Concrete Sidewalk
- Finished Forming and Reinforcing for Paseo Etched Concrete #1
- Finished Placing for Paseo Etched Concrete #1
- Continued Installing Level 1Lobby Accoustibuilt Hard Lid Ceiling
- Started Installing Millwork

Millwork Installation
NEXT WEEK'S ACTIVITIES
- Finish Painting Brass Tap Fence and Installing Hardware
- Finish Forming and Reinforcing for Paseo Stamped Concrete #1
- Finish Placing for Paseo Stamped Concrete #1
- Continue Installing Paseo Underground Electrical
- Continue Installing Millwork

-
Level 1 Lobby Accoustibuilt

Paseo Etched Concrete #1 Placement
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.