Weekly Project Update

Griffith and Paseo

Placeholder

Ian Doyle

Sep 8, 2025

THIS WEEK'S ACCOMPLISHMENT

    Finish Preparing for South Fiber Optic Lights Concrete Pour
    Finished Forming and Reinforcing for Paseo Stamped and Stage Concrete
    Finished Placing Concrete for Paseo Stamped and Stage Concrete
    Continued Installing Ceramic Tile on Level 1
    Continued Installing Outlets and Switches
    Continued Installing New Elevator
Excavation 1.jpg

New Elevator Installation

NEXT WEEK'S ACTIVITIES

    Finish Installing Gallery Spray Foam Insulation
    Finish Installing New Elevator
    Finish Placing Concrete for South Fiber Optic Lights
    Continue Installing Ceramic Tile on Level 1
    Continue Installing Brick around Elevator Entrance
Excavation 1.jpg

Paseo Fiber Optic Light Preparation

Excavation 1.jpg

Paseo Stamped and Staged Concrete

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.