Weekly Project Update

Horseshoe Bay City Hall

Placeholder

Nathan Barry

Oct 12, 2025

THIS WEEK'S ACCOMPLISHMENT

    Complete Water Quality Pond #1 & #2 Construction to 95%
    Complete Landscape & Irrigation to 70%
    Complete Ceramic Tile @ Restrooms
    Pull Secondary Service Wire to Building Disconnect & Energize
    Install 80 % of Ceiling Grid @ Lobby
    Start Fire Alarm System Installation
Excavation 1.jpg

Water Quality Ponds Complete to 95%

NEXT WEEK'S ACTIVITIES

    Receive Plumbing Fixtures for 10-21 Start Installation
    Receive Millwork for Installation starting 10-20-2025
    Install Ceiling Tile Borders Throughout
    Extend Electric to Mechanical Yard Condensers
    Complete Landscaping to 95%
Excavation 1.jpg
    Install Flagpoles

Landscaping Complete to 70%

Excavation 1.jpg

Wednesday Morning 10-8-2025

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.