Weekly Project Update
Horseshoe Bay City Hall

Nathan Barry
Oct 12, 2025
THIS WEEK'S ACCOMPLISHMENT
- Complete Water Quality Pond #1 & #2 Construction to 95%
- Complete Landscape & Irrigation to 70%
- Complete Ceramic Tile @ Restrooms
- Pull Secondary Service Wire to Building Disconnect & Energize
- Install 80 % of Ceiling Grid @ Lobby
- Start Fire Alarm System Installation

Water Quality Ponds Complete to 95%
NEXT WEEK'S ACTIVITIES
- Receive Plumbing Fixtures for 10-21 Start Installation
- Receive Millwork for Installation starting 10-20-2025
- Install Ceiling Tile Borders Throughout
- Extend Electric to Mechanical Yard Condensers
- Complete Landscaping to 95%

- Install Flagpoles
Landscaping Complete to 70%

Wednesday Morning 10-8-2025
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.