THIS WEEK'S ACCOMPLISHMENT
- Complete Exterior Conduit Rough for Patio Lights
- Receive Exterior Metal Wall Panels
- Install Last (3) Large Window Glass @ Lobby
- Complete Ceiling Grid in All Plan West Wing Offices
- Complete All Major Wall Sheetrock
- Continue 1st Finish Coat on Walls @ Lobby & Council Chamber

Continue Vented Metal Soffit @ West Wing Low Roof
NEXT WEEK'S ACTIVITIES
- Install Exterior Metal Wall Panels @ Plan East Restroom
- Complete 80% of Lightning Protection System
- Complete 1st Finish Coat @ Lobby and Council Chamber
- Start Remaining Sidewalk & X-Mas Tree Flatwork
- Continue Storefront Window Break-Metal, Caulk & Trim

- Start Dropping Sprinkler Heads in Office Grid
Install Large Glass @ Lobby Storefront Windows

1st Finish Coat Paint @ Council Chamber