Weekly Project Update

Horseshoe Bay City Hall

Placeholder

Nathan Barry

Aug 31, 2025

THIS WEEK'S ACCOMPLISHMENT

    Complete Exterior Conduit Rough for Patio Lights
    Receive Exterior Metal Wall Panels
    Install Last (3) Large Window Glass @ Lobby
    Complete Ceiling Grid in All Plan West Wing Offices
    Complete All Major Wall Sheetrock
    Continue 1st Finish Coat on Walls @ Lobby & Council Chamber
Excavation 1.jpg

Continue Vented Metal Soffit @ West Wing Low Roof

NEXT WEEK'S ACTIVITIES

    Install Exterior Metal Wall Panels @ Plan East Restroom
    Complete 80% of Lightning Protection System
    Complete 1st Finish Coat @ Lobby and Council Chamber
    Start Remaining Sidewalk & X-Mas Tree Flatwork
    Continue Storefront Window Break-Metal, Caulk & Trim
Excavation 1.jpg
    Start Dropping Sprinkler Heads in Office Grid

Install Large Glass @ Lobby Storefront Windows

Excavation 1.jpg

1st Finish Coat Paint @ Council Chamber

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.