Weekly Project Update
Horseshoe Bay City Hall

Nathan Barry
Jul 13, 2025
THIS WEEK'S ACCOMPLISHMENT
- Pumping Down Pond #2 after excess of 4" RAIN over Weekend
- Complete Plan East Standing Seam Metal Roof Panel Installation
- Complete Plan West Upper Roof Wall Waterproofing - Ready for Hardie Siding
- Fabricate ALL Plan West Lower Roofing Standing Seam Metal Roof Panels
- Receive Interior Sheetrock Wall Board Inspection - Ready to Start Tape & Float
- Continue Data Wire Installation

Pump Down Pond #2 from 4" Weekend Rain
NEXT WEEK'S ACTIVITIES
- Start Hardie Board Siding @ Plan West Upper Roof Walls
- Start Storefront Window Wall Assemblies @ #123 Breakroom & #112 Medium Conference Room
- Complete Sheetrock Top-out of Walls @ Council Chamber & Lobby
- Flush Out 6" Fire Line & Connect to Building Sprinkler Main
- Complete Ductwork to 95%

- Start Tape & Float @ Sheetrock
Continue Top-out of Council Chamber Plan West Wall

Complete Plan East Standing Seam Metal Roof Panels