THIS WEEK'S ACCOMPLISHMENT

    Pumping Down Pond #2 after excess of 4" RAIN over Weekend
    Complete Plan East Standing Seam Metal Roof Panel Installation
    Complete Plan West Upper Roof Wall Waterproofing - Ready for Hardie Siding
    Fabricate ALL Plan West Lower Roofing Standing Seam Metal Roof Panels
    Receive Interior Sheetrock Wall Board Inspection - Ready to Start Tape & Float
    Continue Data Wire Installation
Excavation 1.jpg

Pump Down Pond #2 from 4" Weekend Rain

NEXT WEEK'S ACTIVITIES

    Start Hardie Board Siding @ Plan West Upper Roof Walls
    Start Storefront Window Wall Assemblies @ #123 Breakroom & #112 Medium Conference Room
    Complete Sheetrock Top-out of Walls @ Council Chamber & Lobby
    Flush Out 6" Fire Line & Connect to Building Sprinkler Main
    Complete Ductwork to 95%
Excavation 1.jpg
    Start Tape & Float @ Sheetrock

Continue Top-out of Council Chamber Plan West Wall

Excavation 1.jpg

Complete Plan East Standing Seam Metal Roof Panels