THIS WEEK'S ACCOMPLISHMENT

    Masonry Infill Previous Exterior Monitor Location Near Entry
    Complete HARDIE SIDING on Plan North & East Wall
    Complete Metal Standing Seam Roof Panels @ Plan West Lower Roof
    Sand Plan West Office Walls Prior to Priming & 1st Finish Paint
    Complete 60% Refrigerant Line Set Connection to Mezzanine Mixing Boxes
    Continue Installation of Storefront Window Assemblies @ Plan West Upper Gable
Excavation 1.jpg

Masonry Infill @ Previous Exterior Monitor Location Near Entry

NEXT WEEK'S ACTIVITIES

    Start Prime & 1st Finish Coat of Paint @ Plan West Wing Offices
    Complete HARDIE Siding Plan West Wing @ West Wall
    Complete Standing Seam Roof Panels @ Plan East Restrooms
    Continue Storefront Window Frame Assemblies @ Lobby
    Pressure Test / Inspection of Bldg. Water Piping System
Excavation 1.jpg
    Complete Refrigerant Line Set Connection to Mezzanine Mixing Boxes

Complete HARDIE Siding @ Plan East Wing - North and East Walls

Excavation 1.jpg

Goes Without Saying...

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.