THIS WEEK'S ACCOMPLISHMENT
- Masonry Infill Previous Exterior Monitor Location Near Entry
- Complete HARDIE SIDING on Plan North & East Wall
- Complete Metal Standing Seam Roof Panels @ Plan West Lower Roof
- Sand Plan West Office Walls Prior to Priming & 1st Finish Paint
- Complete 60% Refrigerant Line Set Connection to Mezzanine Mixing Boxes
- Continue Installation of Storefront Window Assemblies @ Plan West Upper Gable

Masonry Infill @ Previous Exterior Monitor Location Near Entry
NEXT WEEK'S ACTIVITIES
- Start Prime & 1st Finish Coat of Paint @ Plan West Wing Offices
- Complete HARDIE Siding Plan West Wing @ West Wall
- Complete Standing Seam Roof Panels @ Plan East Restrooms
- Continue Storefront Window Frame Assemblies @ Lobby
- Pressure Test / Inspection of Bldg. Water Piping System

- Complete Refrigerant Line Set Connection to Mezzanine Mixing Boxes
Complete HARDIE Siding @ Plan East Wing - North and East Walls