Weekly Project Update
Horseshoe Bay City Hall

Nathan Barry
Oct 19, 2025
THIS WEEK'S ACCOMPLISHMENT
- Complete Landscape & Irrigation - Phase 1
- Complete Water Quality Pond #1 & #2 Construction
- Install Canopy @ Plan East Exterior Door
- Received All Plumbing Fixtures
- Complete 80% of Ceramic Tile Flooring
- Install Metal Gates @ Dumpster Enclosure

Grass Sod & Steel Guardrails @ Sidewalk
NEXT WEEK'S ACTIVITIES
- Prepare Site for City's 20TH Anniversary Celebration
- Hydro-Seed Water Quality Ponds #1 & #2
- Install Fire Alarm Devices
- Install SL-1 Light Poles @ Building South Elevation
- Set Limestone Blocks @ Entry & X-Mas Tree Location

- Start Installation of Ceiling Tile Borders
Metal Dumpster Enclosure Gates

Building South Elevation
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.