THIS WEEK'S ACCOMPLISHMENT

    Complete Landscape & Irrigation - Phase 1
    Complete Water Quality Pond #1 & #2 Construction
    Install Canopy @ Plan East Exterior Door
    Received All Plumbing Fixtures
    Complete 80% of Ceramic Tile Flooring
    Install Metal Gates @ Dumpster Enclosure
Excavation 1.jpg

Grass Sod & Steel Guardrails @ Sidewalk

NEXT WEEK'S ACTIVITIES

    Prepare Site for City's 20TH Anniversary Celebration
    Hydro-Seed Water Quality Ponds #1 & #2
    Install Fire Alarm Devices
    Install SL-1 Light Poles @ Building South Elevation
    Set Limestone Blocks @ Entry & X-Mas Tree Location
Excavation 1.jpg
    Start Installation of Ceiling Tile Borders

Metal Dumpster Enclosure Gates

Excavation 1.jpg

Building South Elevation