Weekly Project Update

Horseshoe Bay City Hall

Placeholder

Nathan Barry

Aug 24, 2025

THIS WEEK'S ACCOMPLISHMENT

    Start Final Sidewalk Grading
    Continue Caulking & Trim Installation @ Storefront Window Assemblies
    Continue Metal Vented Soffit Panels at Council Chamber East Wing
    Continue 1st Paint Finish Coat @ All Plan West Wing Walls
    Start Acoustical Ceiling Grid @ Plan West Wing Offices
    Install Steel Lavatory Support Frames @ All Restrooms
Excavation 1.jpg

Start Office Storefront Door Frame Installation

NEXT WEEK'S ACTIVITIES

    Complete Electric Conduit Rough to All Exterior Lights @ Patio
    Continue Vented Metal Soffit Panels @ Plan West Low Roof
    Install Final Large Window Glass @ Lobby Storefront Assemblies
    Complete 80% Ceiling Grid @ Plan West Wing Offices
    Complete 95% Wall Sheetrock
Excavation 1.jpg
    Install 1st Finish Coat on Walls @ Council Chamber

Start Ceiling Grid Installation @ Offices

Excavation 1.jpg

Start Prime & 1st Finish Coat @ Council Chamber