Weekly Project Update
Horseshoe Bay City Hall

Nathan Barry
Aug 24, 2025
THIS WEEK'S ACCOMPLISHMENT
- Start Final Sidewalk Grading
- Continue Caulking & Trim Installation @ Storefront Window Assemblies
- Continue Metal Vented Soffit Panels at Council Chamber East Wing
- Continue 1st Paint Finish Coat @ All Plan West Wing Walls
- Start Acoustical Ceiling Grid @ Plan West Wing Offices
- Install Steel Lavatory Support Frames @ All Restrooms

Start Office Storefront Door Frame Installation
NEXT WEEK'S ACTIVITIES
- Complete Electric Conduit Rough to All Exterior Lights @ Patio
- Continue Vented Metal Soffit Panels @ Plan West Low Roof
- Install Final Large Window Glass @ Lobby Storefront Assemblies
- Complete 80% Ceiling Grid @ Plan West Wing Offices
- Complete 95% Wall Sheetrock

- Install 1st Finish Coat on Walls @ Council Chamber
Start Ceiling Grid Installation @ Offices

Start Prime & 1st Finish Coat @ Council Chamber
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.